Practice question 166 of 180 · hard
Staff begin signing in at 08:30 local time. Tested hosts need ten minutes from a power-on request to launch readiness. Ramp-up currently begins at 08:30 in the correct time zone. The business requires capacity ready five minutes before sign-ins. When should ramp-up begin at the latest?
Choose the single best answer.
Show the answer and explanation
✓ Correct answer
- 08:15 local time.
Schedule capacity ahead of demand: 08:30 minus five minutes of readiness margin minus ten minutes of measured startup is 08:15. Monitor actual readiness rather than assuming power-on means launch-ready. Option explanations: A. 08:20 local time.: Preparation completes at 08:30, leaving no required five-minute readiness margin. B. 08:25 local time.: Preparation completes at 08:35, after users begin signing in. C. 08:15 local time.: Ten minutes of preparation completes by 08:25, five minutes before the sign-in wave. D. 08:30 local time.: This requests power at the start of demand instead of preparing capacity beforehand. Sources: Create a scaling plan — https://learn.microsoft.com/en-us/azure/virtual-desktop/autoscale-create-assign-scaling-plan
Read and review here, or open the app to practise and save your results on this device.
Unofficial study aid, not affiliated with or endorsed by Microsoft. Original educational practice questions, not official exam questions or a prediction of an exam result. Use Microsoft Learn and hands-on labs alongside this course.