An adoption team has agreed on business outcomes but has not prepared skills, workload priorities, ownership, or funding. Which CAF phase most directly addresses the missing work?

Choose the single best answer.

  1. A.Plan
  2. B.Adopt
  3. C.Ready
  4. D.Manage
Show the answer and explanation

✓ Correct answer

  • Plan

Plan prepares skills, costs, priorities, ownership, and adoption work. Ready establishes the Azure foundation; Adopt executes migration and modernization; Manage operates and improves adopted workloads. Source guide: PDF page(s) 4.