Practice question 270 of 400 · medium
New Batch nodes need a controlled software preparation step before tasks run. Which Batch concept should be used?
Choose the single best answer.
Show the answer and explanation
✓ Correct answer
- A pool start task or controlled image/application package
Start tasks and controlled images/packages prepare nodes. Job release runs after work, dependencies order tasks without supplying missing software, and autoscale changes capacity rather than installation. Source guide: PDF page(s) 48.