A research application uses tightly coupled MPI work across several nodes. Which Batch capability should be evaluated?

Choose the single best answer.

  1. A.A dependency graph waiting for separate single-node tasks to finish
  2. B.Pool autoscale alone with ordinary single-node commands
  3. C.Multi-instance tasks with compatible node, network, and coordination requirements
  4. D.Independent single-node tasks without cross-node coordination
Show the answer and explanation

✓ Correct answer

  • Multi-instance tasks with compatible node, network, and coordination requirements

Multi-instance tasks coordinate supported tightly coupled MPI execution. Uncoordinated tasks, capacity autoscale alone, and completion dependencies between separate single-node commands do not supply simultaneous distributed execution and communication. Source guide: PDF page(s) 48.

Read the source reference

This item is flagged for content review.

Read and review here, or open the app to practise and save your results on this device.

Unofficial study aid; not affiliated with or endorsed by Microsoft. Original practice questions are not real examination questions and do not guarantee an exam result.