Practice question 170 of 400 · hard
A timestamp-watermark pipeline uses modification time but misses deleted rows and some equal-timestamp updates. What is the best next step?
Choose the single best answer.
Show the answer and explanation
✓ Correct answer
- Design correct watermark boundaries and deletion handling or use supported CDC, then reconcile business totals
The fault is incomplete change capture. Robust boundaries/deletion handling or supported CDC addresses it; reconciliation proves effects. Faster destination compute and activity success do not correct missing changes, and losing tracked progress worsens recovery. Source guide: PDF page 32.
This item is flagged for content review.
Read and review here, or open the app to practise and save your results on this device.
Unofficial study aid; not affiliated with or endorsed by Microsoft. Original practice questions are not real examination questions and do not guarantee an exam result.