A server inventory has been imported into Azure Migrate. The team assumes the applications have now migrated. Which statement clarifies the result?

Choose the single best answer.

  1. A.Assessment results are equivalent to a completed production cutover
  2. B.Inventory import installs all application dependencies on PaaS
  3. C.Every inventoried VM automatically starts in the target subscription
  4. D.Inventory import can support discovery but does not copy workloads
Show the answer and explanation

✓ Correct answer

  • Inventory import can support discovery but does not copy workloads

Discovery identifies assets; assessment evaluates readiness and sizing; migration copies or replicates them. Inventory does not start VMs, install a PaaS application, or complete cutover. Source guide: PDF page(s) 62.

Read the source reference

This item is flagged for content review.

Read and review here, or open the app to practise and save your results on this device.

Unofficial study aid; not affiliated with or endorsed by Microsoft. Original practice questions are not real examination questions and do not guarantee an exam result.