A stateful application is ready to cut over. Which two actions directly support a consistent switch? Select two answers.
Select all that apply. Every correct option and no extras are required for credit in the app.
Show the answer and explanation
✓ Correct answers
- Start target dependencies in order and validate transactions before release
- Quiesce source writes as required and synchronize final changes
Final synchronization and dependency-aware startup support a controlled switch. Uncoordinated dual writers can diverge; premature routing exposes unready services; deleting backups removes recovery options. Source guide: PDF page(s) 62-63.