Practice question 148 of 506 · hard
The primary site is unavailable. A replica can start, but its last received changes are several minutes old. Which expectation is correct for an unplanned failover?
Choose the single best answer.
Show the answer and explanation
✓ Correct answer
- Unsent primary changes may be lost, so choose the recovery point and fence the old primary
Asynchronous replication cannot restore unsent changes, and fencing avoids competing copies. VM configuration does not contain all unsent transactions. Parallel activation creates conflict risk. Zero loss depends on a successful coordinated final transfer during planned failover, which is unavailable here.
Read and review here, or open the app to practise and save your results on this device.
Unofficial study material, independently written and not affiliated with or endorsed by Microsoft. These are original learning questions, not actual exam questions. Product support and exam scope can change; a practice percentage is not a Microsoft exam scaled score.