Practice question 379 of 506 · easy
A disk-latency incident occurs only at 02:00. Which approach best collects evidence?
Choose the single best answer.
Show the answer and explanation
✓ Correct answer
- Schedule a DCS with disk and workload counters
A scheduled DCS captures the overnight incident with relevant correlated counters. A noon chart and one later sample miss the incident period. A definition that never runs does not produce data.