Practice question 488 of 498 · hard
A regional recovery rehearsal restores a database in 45 minutes, meeting the technical restore estimate. Customers still cannot use the service because private name resolution and key access take another 80 minutes to recover. The business RTO is 90 minutes. Which assessment is most accurate?
Choose the single best answer.
Show the answer and explanation
✓ Correct answer
- The full service requires 125 minutes, so redesign the dependency recovery path before declaring the RTO met
The full service requires 125 minutes, so redesign the dependency recovery path before declaring the RTO met: The sequential dependency delay and data restoration together exceed the business restoration target. The RTO is met because the database restore took less than 90 minutes: A component estimate is insufficient when the business service is still unusable. The RPO is 125 minutes because key access was delayed: RPO measures tolerated data loss rather than restoration duration. Keep the plan unchanged and remove encryption to make the recovery report simpler: The requirement calls for secure, usable recovery and a tested dependency design. Double replication frequency and assume dependency timing no longer matters: Replication frequency does not repair name resolution or key authorization.
Read and review here, or open the app to practise and save your results on this device.
Unofficial study material. Not affiliated with or endorsed by Microsoft. These are original learning questions, not actual exam questions. Product capabilities and exam objectives can change; verify current Microsoft documentation. Practice scores do not predict or guarantee an exam result.